
Gallery
The Footers, Foundation and the Wall
-
The excavation for the house
-
2 inch thick extra dense EPS under footers
-
Sides of footers also receive 2 inches of EPS
-
Footers are extra wide to spread pressure
Rebar structure starts for the Wall
-
Rebar work continues
-
Footers positions set by satellite survey technology
-
Reinforcing forms
-
Foaming gaps in EPS forms
-
Sealing gaps prevent heat sink thermal breaks
-
The concrete pours begins!
-
50% fly ash concrete mixture
-
It's a long reach to the far corner
-
Rebar added while concrete setting for foundation
-
A total of 7 loads of concrete used
-
Footers viewed from West
-
Concrete production responsible for 10% World's CO2 production
-
Forms stripped from footers revealing EPS
-
Forms left in place longer for 50% fly ash concrete
-
50% fly ash concrete cures twice as strong
-
The "Wall" forms with PVC tubes for PCM wax
-
The "Wall" 18 ½ feet tall, over 100 feet long, 16 inches thick
-
Thermal Break of the "Wall" using plastic rebar and 4 inches EPS
-
Construction of the "Wall" forms
-
Pouring the "Wall"
-
The "Wall" pour finished, no blowouts, EPS thermal break, tubes for PCM wax
Vasily contemplating the thermodynamics of the "Wall"
A total of three 55 gallon barrels were used to fill the "Wall"
PCM wax being pumped into the "Wall"
The PCM wax holds 3000 BTU's per cubic foot per degree F (100 times that of concrete)
-
Pouring the foundation walls
-
The "Wall" revealed
-
The "Wall" seen from behind
-
The 'Wall" and foundation required 10 loads of cement
-
The exposed "Wall" will be made into a climbing wall
-
Readying the pour to form the roof of the mechanical room
-
Roof poured with openings for plumbing, electrical, HRV etc
-
Wing insulation for Shallow Depth Frost Protected (SDFP) footers
-
Back Filling over SDFP wing insulation, 10 inches
-
Todd adding EPS to the top of the footers and sealing gaps
-
Vapor barrier atop the insulated footers
-
Foundation and wing insulation, Radon mitigation tubing
-
Gravel infill prior to adding 8 inches EPS (R32)
-
Mechanical room, polymer based waterproofing, Ecobase
-
Wing insulation sealed, vapor barrier in place, Ecobase atop foundation, Radon tubing
-
Insulation atop garage foundation
-
Wing insulation, insulated footers/foundation with vapor barrier and Ecobase sealing
-
8 inches EPS (R32) added to exterior of the "Wall" below frost line
-
"Wall" insulation, footers with 4 inches EPS and Vapor barrier, French drain
-
Garage floor drains
-
The "Wall" from behind
-
Mechanical room Ecobase sealed and ready for 12 inches EPS
-
Plumbing drains in place, fine gravel infill
-
Laying down two 4 inch layers of EPS (R32) with vapor barrier between
-
Concrete cuts for drains in footers will be covered with 4 inches EPs
-
Installing radiant heat tubing
-
Tubing attached to metal grid work
-
Larger diameter tubing (3/4") to decrease flow restrictions
-
Tubing in place, oversized couplers used
-
Tubing with wall placement, spray painted on
-
Mechanical Room with 12 inches EPS (R48) installed
-
Garage floor cement pour, rebar and vapor barrier
-
Using power trowel to smooth concrete
-
Creating slope to drains
-
Hand finishing garage floor
-
Power troweling first floor to a shiny smoothness, later will be stained
-
Incredibly smooth finish, radon mitigation pipe in background
-
Cement cut to deflect future cracking